News about the upcoming tribe change
After procurement, a contract has been signed with the company Nordic Plumbing who will carry out the tribal change for the association. It is the same contractor who did the work in the neighboring associations and the board feels confident that it will be a good project.
After the summer, the project will continue to work with all the other details that must be prepared.
Preliminary timetable for port 27
According to the preliminary schedule, the trunk change will begin in port 27 in week 2, 2022. The renovation is being run trunk and all apartments that end with the same apartment number (the tax authority's 4 digits) belong to a trunk.
Phase 1 | Week 2 to 10 | Apartmentnumber ending in 4 and 5 |
Phase 2 | Week 5 to 12 | Apartmentnumber ending in 1 and 2 |
Phase 3 | Week 9 to 18 | Apartmentnumber ending in 3 and 2 |
Phase 4 | Week 13 to 21 | Apartmentnumber ending in 3 and 4 |
Definitive schedule will be published later. Meetings will be booked at the end of October with the residents affected in the first phase.
- All residents can prepare by:
- read up on the documents that are under folder stambyte on the document site NABO (www.nabo.se, log in with bank ID).
- Current information will also be published on side of the stem change.
- Questions and thoughts arise that way contact the board.
- It is extra important that those who have moved in after the Extraordinary General Meeting (February 2021) absorb the above information.
If you want information in paper form, contact the board via the association's mailbox in port 25.