Monthly letter from NCC & Aros Bostad
This news is written by NCC and Aro's home.
Hello neighbors!
The works are progressing according to plan.
In stage 2 of Ncc Bostad, frame work is underway mid-November. Roofing work continues. For the construction crane, removal is planned for the first week of December if everything goes as planned. Demolition of the scaffolding and completion of the facade towards Stage 1 is estimated to be on target by the end of the year.
Our colleagues Ncc Civil continue with the loosening of rock and unloading of rock masses for Stage 3.
In week 45, work begins on widening Gärde's slope for future work on both sides of the road.
On the site for Stage 4, where we have our establishment today, the trees have been taken down and test drilling for geotechnical investigations is underway. The construction of Stage 4 is further down the line, we refer questions regarding it to Aros Housing Development.
We work continuously with the logistics in and around the area to maintain a high level of security and minimize the inconvenience for nearby residents and other interested parties.
In general, we will have a lot of heavy traffic in the area during the entire construction. Therefore, take extra care of children and take care of yourselves. One accident is one accident too many!
As usual, you can always get hold of us via our email Inverneskv1@ncc.se.
With hope for a nice autumn!
Site management Inverness quarter 2 and quarter 3