Monthly letter from NCC & Aros Bostad
This news is written by NCC & Aros Bostad.
Hello neighbors
Autumn is creeping closer to us, but we are still working on it. With the darkness come new challenges and we will set up lighting in the area that will shine during working hours. Since we have a lot of traffic in and out of the area, feel free to be a little attentive around the area.
As usual, you can always get in touch with us via our e-mail Invernesskv1@ncc.se
We also want to ask you to understand the large ship plates that are on the bike path, they are there to prevent accidents and your safety. Below is a brief description of what will happen on the project during weeks 41-46.
In general, we will have a lot of traffic in the area throughout the construction. Therefore, have extra supervision over children and be afraid of you. An accident is an accident too much.
The times and work presented below are preliminary and subject to change.
V.42
- # 3 - Plumbing work
- # 1 and 3 - Drilling of stays
- # 3 - Earth shaft
V.43
- # 1 and 3 - test drawing of struts on the tongue
- # 3 - Plumbing work
- # 3 - Earth shaft
- # 1 - Drilling of stays
V.44
- # 2 - Earth shaft
- # 3 - Plumbing work
V.45
- # 2 - Earth shaft
- # 2 - Blowing rocks
- # 1 and 3 - Test drawing of struts for tongue and groove
V.46
- # 2 - Start for preparatory blasting work
- # 2 - Drills dynamite holes in rock
- # 2 - blow mountains