Monthly letter from NCC & Aros Bostad
This news is written by NCC & Aros Bostad.
Hello neighbors!
As you have probably noticed, we have started with the new stage Inverness Kv.2 now after the summer, we think it's great fun. But as usual, you can always reach us via our e-mail. invernesskv1@ncc.se
In the near future, it is the foundation work that will take off for the new stage. This means that we will build two different tongue and groove, one drilled and one beaten. At the same time, excavation work is also underway as we will make room for a new garage with two floors. We will also use a compressor to blow clean rock as preparatory work for future blasting work.
To easily get hold of someone responsible for the project, we have created our own e-mail address. Get in touch with questions and comments invernesskv1@ncc.se
Below is a brief description of what will happen on the project during weeks 35-40.
In general, we will have a lot of traffic in the area throughout the construction. Therefore, have extra supervision over children and be afraid of you. An accident is an accident too much.
The times and work presented below are preliminary and subject to change.
V.36
- # 1 - Drilling of steel pipes for the Berlinersponten
- # 1 - Welding of steel sheets on the Berlinersponten
- # 3 - Start for the beaten tongue on the east side of the construction area
- # 2 - Earth shaft
V.37
- # 1 - Drilling of stays on the Berlin bridge
- # 1 - Welding of steel sheets on the Berlinersponten
- # 1 - Welding of hammer band beam on the Berlin bridge
- # 3 - Shaft for hammer band beam at Larsensponten
- # 2 - Earth shaft
V.38
- # 1 - Welding of steel sheets on Berlinerspont
- # 3 - Hammarbandsbalk Larsenspont
- # 2 - Blow rock with compressor
- # 2 - Earth shaft
V.39
- # 2 - Blowing rocks
- # 1 & 3 - Test drawing of struts for tongue and groove
- # 2 - Earth shaft
V.40
- # 2 - Start for preparatory blasting work
- # 2 - Drills dynamite holes in rock
- # 2 - blow mountains