Monthly letter from NCC & Aros Bostad - October
This news is written by NCC and Aros Bostad
Hello neighbors
Autumn has started a little with colder weather and darker evenings.
During Oct-Nov we will finish the work with the frame and go over to the roof, facade and interior.
We have ongoing problems with unauthorized people entering the workplace area during evenings and weekends. IN
In connection with these intrusions, we have been exposed to cable theft and vandalism such as graffiti, emptied
fire extinguishers etc. Feel free to keep a watchful eye and do not hesitate to contact the police if you see
slightly outside our regular working hours.
To easily get hold of someone responsible for the project, we have created our own e-mail address. Get in touch with questions
and comments to Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during weeks 37-41.
In general, we will have a lot of traffic in area # 4 (yellow) throughout the construction. Therefore have extra
supervision of children and be afraid of you. An accident is an accident too much.
The times and work presented below are preliminary and subject to change.
V.42
# 2 - Unloading site of material "flag guard when unloading trucks"
# 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 2
# 3 - Roof and facade work starts Staircase 1
V.43
# 2 - Unloading site of material "flag guard when unloading trucks"
# 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 2
# 3 - Roof facade Staircase 1
V.44
# 2 - Unloading site of material "flag guard when unloading trucks"
# 3 - Frame completion Staircase 1
# 3 - Roof facade Staircase 1
V.45
# 2 - Unloading site of material "flag guard when unloading trucks"
# 3 - Frame completion Staircase 1
# 3 - Roof facade Staircase 1
V.46
# 2 - Unloading site of material "flag guard when unloading trucks"
# 3 - Frame completion Staircase 1
# 3 - Roof facade Staircase 2
Project Inverness Kv.1
Monthly letter Oct 2020