Monthly letter from NCC & Aros Bostad - June
This news is written by NCC and Aros Bostad.
Hello good neighbors
Holidays are approaching and this will be the last monthly letter for a while. You will receive the next monthly letter in week 33 (August).
The work for us is very repetitive and the house grows by about one floor per month. Before we go on holiday in week 29, we make sure to be extra careful with cleaning and fencing. We will have extra surveillance of the area during the holiday and also ask your neighbors for help. If you see anything suspicious, movements inside the work area or holes in the fence, we want you to contact the police and also send us an email at invernesskv1@ncc.se.
If you have other questions, you are of course still welcome to contact us at the same email address.
Please
NCC's site management
Hello good neighbors
The summer heat has come and the holidays are approaching. NCC Infra has completed its work with backfilling around the house and we at NCC Bostad have had time to cast the second part of what we call Böp 12 (Floor Over Plan 12 (two floors above street level / entrance level)).
Before we take a holiday during weeks 29-31, we will have cast 4 of 5 parts of Böp 13. During week 28, we will have a smaller force in place to carry out the last work before the holiday and secure the workplace a little extra. When we take a holiday, we will also put in extra surveillance of the area to minimize the risk of burglary and theft. We ask you residents to be extra vigilant and contact the police directly if you see movements inside the work area. Thanks in advance!
To easily get hold of someone responsible for the project, we have created our own e-mail address. Get in touch with questions and comments Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during weeks 24-33.
The times and work presented below are preliminary and subject to change.
V.24
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Stairs 4
V.25
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Stairs 1
V.26
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 2 and 3
V.27
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 3 and 4
V.28
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Stairs 4
V.29-31
- Holiday season
V.32
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Stairs 1
V.33
- #2 - Disposal site of material "flag guard when loading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Stairs 2