Monthly letter from NCC & Aros Bostad - March
This news is written by NCC and Aros Bostad.
Then it was time for info about the construction of Inverness Kv1 again!
The evening work is over for this time (and we hope to avoid more of that kind). We hope it has not been too difficult.
Now you will start to notice more difference from day to day when the housing spin starts. We will have significantly more heavy transports for the construction with flat supports and outer walls as well as concrete transports. About one floor will grow every month!
With that said, we hope that you contact us if you see something that looks uncertain and unsafe or if you have other thoughts about the construction.
Please
NCC's site management
Soon the whole winter has passed and we have had a very good winter when it comes to construction weather.
Now we look forward to a nice spring with sun and warm spring days
During weeks 12–13, we will lay the last part of the courtyard, which is part of the intended walkway that leads over the E18. And with that, there will be a lot of heavy transports into the field on the construction site. In the coming months, the house will grow by about 1 floor a month
In order to easily find someone responsible for the project, we have created our own e-mail address. Please inquire with questions and comments Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during weeks 12-16
The times and work steps presented below are preliminary and may change.
V.12
- # 2 - Unloading site of material "flag guard when unloading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 2
- # 1 - Installation of Floor courtyard
V.13
- # 2 - Unloading site of material "flag guard when unloading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 3
- # 1 - Installation of Floor courtyard
- Start backfilling around Basements
V.14
- # 2 - Unloading site of material "flag guard when unloading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 4
- Continued backfilling around Basements
V.15
- # 2 - Unloading site of material "flag guard when unloading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 1
- Continued backfilling around Basements
V.16
- # 2 - Unloading site of material "flag guard when unloading trucks"
- # 3 - Casting interior walls, Mounting exterior walls and Floor Staircase 2
- Continued backfilling around Basements