Hi
Last month we forgot to send out a month letter, but now it's time again!
What stands out in the coming weeks is an evening assembly that will take place during the weeks 9-10, weekdays at 15.00-22.00. During that time, heavy transport will back up Mörbylund to the unloading pocket we have outside the preschool Prästkragen, of course with pilots.
Christmas has now passed and we are moving towards brighter times. We continue according to the plans and it progresses according to plan and time planning
During week 9-10 we will also work evening 15.00-22.00 with mounting Bjälklaget on the courtyard. And with that, a lot of heavy transport will go into the building. But as usual, we will have flag guards piloting the heavy transport.
In order to easily find someone responsible for the project, we have created our own e-mail address. Please inquire with questions and comments Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during weeks 7-11. The times and work presented below are preliminary and subject to change.
Week 7
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming reinforcement, beams and walls
- # 4 - Mounting of the first Housing Plan Staircase 1
Week 8
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Molding, casting of beams and wall
- # 4 - Casting of first floor plan Staircase 1
Week 9
- #2 - Disposal site of material "flag guard when loading trucks"
- #1 - Forming reinforcement, beams and walls
- # 3 - Mounting of Beamed courtyard 15-22
Week 10
- #2 - Disposal site of material "flag guard when loading trucks"
- #1 - Forming reinforcement, beams and walls
- # 3 - Mounting of Beamed courtyard 15-22
Week 11
- #3 - Forming, molding of beams and wall garage
- #2 - Disposal site of material "flag guard when loading trucks"
- # 1 - Installation of Beamed garage