Monthly letter from NCC & Aros Bostad - December
This news is written by NCC and Aros Bostad.
The original text is available for download PDF format here.
Hey! Soon Christmas is here and the first snow has fallen. Our work on the garage is ticking according to plan. And we have clearly laid the bottom plate for the entire Kv.1
NCC Infra continues with the backfill against molded walls around garage walls until Christmas
To easily get hold of someone responsible for the project, we have created our own e-mail address. Please inquire with questions and comments to Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during the weeks
The times and work presented below are preliminary and subject to change.
V.50
- #2 - Disposal site of material "flag guard when loading trucks" when loading trucks "
- #3 - Forming reinforcement, beams and walls
- #1 - Backfill of basement walls garage
V.51
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, molding of beams and wall
- #1 - Backfill of basement walls garage
V.52
- Closed for Christmas
V.01
- Closed for Christmas
V.02
- #2 - Installation of the first Housing Plan Trapphus 4 "# 5" unloading of trucks for this will be on Wednesday and Thursday about 09:00 both days
- #3 - Forming, casting of beams and wall garage
- #2 - Disposal site of material "flag guard when loading trucks"