Monthly letter from NCC & Aros Bostad - October
This news is written by NCC and Aros Bostad.
The original text is available download in PDF format here.
Hello again
Time for the October report on the progress of the building.
We have started with walls in the garage and are working full time to catch up with the next milestone: mounting the hole deck (#1), starting Monday 43.
To catch up with everything that is needed, our colleagues at NCC Infra will work up to 18.00 some days. What they do then is refill around foundations and beams. We thank you in advance for your compassion for this.
Weeks go and autumn is here with colder, darker mornings. Our work with the garage is ticking according to our plan and planning.
NCC Infra will continue its work to restore after district heating shaft on the Forest Trail. Asphalting is now complete and fine planning is underway
To easily get hold of someone responsible for the project, we have created our own e-mail address. Get in touch with questions and comments Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during week 42
The times and work presented below are preliminary and subject to change.
V.42
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Molding reinforcement, casting of slabs, beams and walls
- #4 - Recovery work after district heating shaft fin planning
V.43
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #1 - Mounting of Beams Garage
- #4 - Recovery work after district heating shaft fin planning
V.44
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #1 - Mounting of Beams Garage + Casting
V.45
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #1 - Casting of Beams Garage