Monthly letter from NCC & Aros Bostad - September
This news is written by NCC and Aros Bostad.
The original text is available download in PDF format here.
Hi
The weeks go by and autumn begins to knock on the door. Our work with the garage is ticking according to our plan and planning.
Mikael Sjögren is the last we will present in the plastic line for houses. In his role in the project, he is responsible for the economy and administration. He is a happy man with a big heart and a natural interest. And then it has become natural to become a leader in the Scouts.
NCC Infra will continue its work to restore after district heating shaft on the Forest Trail. Asphalting is now complete and fine planning is underway.
To easily get hold of someone responsible for the project, we have created our own e-mail address. Please inquire with questions and comments to Invernesskv1@ncc.se
Below is a brief description of what will happen on the project during week 38 - 41 The times and work presented below are preliminary and may change.
V.38
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Molding reinforcement, casting of slabs, beams and walls
- #4 - Recovery work after district heating shaft fin planning
V.39
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #4 - Recovery work after district heating shaft fin planning
V.40
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #4 - Recovery work after district heating shaft fin planning
V.41
- #2 - Disposal site of material "flag guard when loading trucks"
- #3 - Forming, casting of beams and foundations
- #4 - Recovery work after district heating shaft fin planning