Monthly letter from NCC & Aros Bostad - July
This news is written by NCC and Aros Bostad.
The original text is available download in PDF format here.
Hi
Now it is approaching holidays and sweet bread days, but Bostad will have some small jobs left in the pit during week 28.
The supervisor who will be responsible during that week is Emil Netz. Outside of work, he is a lifelong hockey referee and referee trainer who likes to stay in shape with martial arts training as well as long walks with co-workers.
NCC Infra will continue its work on roads and conduits.
To easily get hold of someone responsible for the project, we have created our own e-mail address. Get in touch with questions and comments invernesskv1@ncc.se
Below is a brief description of what will happen on the project during week 28. The times and work presented below are preliminary and subject to change.
V.28
- #1 - Switching gates
- #2 - Complement of shell protection (fence and heavy shutter)
- #3 - Forming beams and foundations
- #4 - NCC Infra continues to refill the shaft for new district heating line
V.29-31
- Holiday season
V.32
- #3 - Forming beams and foundations
- #4 - Recovery work after district heating shaft
- #5 - Complementary piling (noise)
V.33
- #3 - Forming beams and foundations
- #4 - Recovery work after district heating shaft, paving (Thursday)
- #6 - Installation of tower crane (may affect traffic and pedestrians when entering the building area)